The Hon’ble High Court of Jammu & Kashmir and Ladakh at Srinagar, in J&K Lakes & Waterways Development Authority & Ors. v. Mohammad Amin Shah (A.A. No. 9900001/2014), decided on August 29, 2026, dismissed a petition under Section 34 of the J&K Arbitration and Conciliation Act, 1997, challenging an arbitral award of ₹21,19,439/- in favour of the Contractor. The Hon’ble Court held that the arbitrator’s interpretation of the contractual provisions was a possible and reasonable view and did not warrant interference under Section 34.
The dispute arose from a contract awarded by the Jammu & Kashmir Lakes and Waterways Development Authority (“L&WDA”) for construction of a sewer line along the Nigeen fringe. The Contractor claimed compensation for additional dewatering, idle labour and machinery, escalation and other losses arising from L&WDA’s failure to supply RCC spun pipes and make the requisite site available. The arbitrator found that the delays were attributable to L&WDA and awarded ₹21,19,439/- under various heads.
L&WDA challenged the award principally on the basis of Clauses 21, 23 and 34 of the contract. It contended that these provisions restricted compensation for suspension or abandonment of work, dewatering and loss or damage to departmental materials and that the arbitrator had therefore acted contrary to the contract.
The Hon’ble Court reiterated that Section 34 proceedings are supervisory and not appellate in nature and that an award cannot be interfered with merely because another interpretation of the contract is possible. With respect to Clause 21, the Hon’ble Court held that its restriction applied where suspension or abandonment occurred on the directions of L&WDA, which was not the case here. Clause 23 did not bar a claim for additional dewatering caused by L&WDA’s delay, while Clause 34 concerning departmental materials could not be extended to losses suffered by the Contractor.
The Hon’ble Court further upheld the award of escalation, noting that the arbitrator had restricted the claim to 4% based on L&WDA’s own recommendation and the All India Price Index. The absence of an escalation clause did not preclude compensation for additional costs resulting from delay attributable to the employer.
Accordingly, the Hon’ble Court held that the arbitrator’s findings were supported by the evidence and that no patent illegality or conflict with public policy was established. The petition under Section 34 was dismissed, and the arbitral award was allowed to stand.