The National Highways Authority of India (NHAI) has introduced a uniform mechanism for independent verification of the designs and drawings of major bridges and other critical structures in National Highway projects. The policy, effective from December 1, 2026, seeks to strengthen structural safety, durability and quality assurance by identifying potential design deficiencies before construction.
The framework covers major bridges and viaducts, including river bridges with a design discharge of at least 3,000 cubic metres per second, structures with an individual effective span of 40 metres or more and other special or complex structures identified by NHAI.
Independent verification will be undertaken by institutions and firms empanelled by NHAI, including Indian Institutes of Technology (IITs), reputed government technical institutions and experienced technical firms specialising in bridge engineering and hydraulic studies. The review will cover structural design calculations, structural analysis, design drawings and, wherever applicable, hydrological and hydraulic studies, including assessments of water flow, flood levels and foundation safety against river-bed erosion.
Under the prescribed procedure, the contractor or concessionaire will first submit the designs and drawings to the Authority’s Engineer or Independent Engineer for review or approval in accordance with the applicable contract. Thereafter, three institutions or firms will be proposed from NHAI’s empanelled list, from which one or more will be selected to undertake the independent verification. The contractor or concessionaire must consider the observations and recommendations received and make the necessary design modifications before the design is reviewed or approved by NHAI under the applicable contractual provisions.
The policy will apply to new Engineering, Procurement and Construction (EPC), Hybrid Annuity Model (HAM) and Build-Operate-Transfer (BOT) National Highway projects, as well as projects in which design verification or proof-checking has not commenced. Projects where such verification has already been completed will generally be excluded, although NHAI may require additional checks for major bridges and complex or critical special structures.
The introduction of independent design scrutiny establishes an additional quality-assurance requirement at the design stage of highway projects. For contractors and concessionaires, this is likely to require closer coordination between designers, proof-checkers and project teams, particularly in relation to design submissions, responses to technical observations and the incorporation of revisions within project timelines.